Guide · Contractors

Mechanics Lien Deadlines in 10 States: Notices, Liens and Lawsuits (2026)

Every notice, lien and lawsuit deadline for private projects in the 10 largest construction states, with the statute behind each one.

Rules checked October 21, 2026 against State statutes: CA, TX, FL, NY, GA, AZ, WA, NC, CO, IL. Next scheduled check: November 20, 2026. See all rule updates
The short answer

Lien deadlines run from the days you actually worked or delivered materials, or from project completion, never from your invoice. Most states give 90 to 120 days to file the lien itself, New York gives up to 8 months, and many states require a preliminary notice within the first 15 to 45 days of the job.

Use the free calculator to get every date for your job.

Why invoice dates are the wrong start date

Contractors often count from the date they billed. The statutes count from when work was performed or materials were furnished, or from completion of the project. If you finished in March and invoiced in April, a Florida lien is still due 90 days after the March work, not the April invoice. In a survey of subcontractors, 56% said they had missed a critical lien deadline in the past two years.

Two other dates trip people up: warranty or punch-list work usually does not restart the clock, and in California and Arizona the owner can shorten your window by recording a notice of completion.

Deadlines in 10 states

Private projects. Deadlines can change with retainage claims, contract terms and recorded notices.

StatePreliminary noticeFile the lienSue to enforceStatute
California20 days after first furnishing (most claimants not hired by the owner)Earlier of 90 days after project completion, or 30 days (subs) / 60 days (direct contractors) after a recorded notice of completion90 days after recordingCiv. Code §§ 8204, 8412, 8414, 8460
TexasSubs and suppliers: 15th day of the 3rd month after each month worked (2nd month, residential)15th day of the 4th month after the last month worked (3rd month, residential)1 year after the last day to fileProp. Code §§ 53.052, 53.056, 53.158
FloridaNotice to Owner within 45 days of starting (subs and suppliers)90 days after final furnishing1 year after recordingFla. Stat. §§ 713.06, 713.08, 713.22
New YorkNone8 months after completion or final work (4 months, single-family home)Lien lasts 1 year after filing unless extended or foreclosedLien Law §§ 10, 11, 17
GeorgiaOptional notice of lien rights within 30 days; notice to contractor if a Notice of Commencement was filed90 days after completing work or last delivery365 days after filingO.C.G.A. §§ 44-14-361.1, 361.3, 361.5
Arizona20-day preliminary notice (all claimants except wage laborers)120 days after completion, or 60 days after a recorded notice of completion6 months after recordingA.R.S. §§ 33-992.01, 33-993, 33-998
WashingtonNotice to owner within 60 days of first furnishing (subs not hired by the prime)90 days after last furnishing8 months after recordingRCW 60.04.031, .091, .141
North CarolinaNotice to lien agent within 15 days ($40,000+ projects with a lien agent)120 days after last furnishing180 days after last furnishingG.S. 44A-11.2, 44A-12, 44A-13
ColoradoNotice of intent at least 10 days before recording4 months after last work6 months after last workC.R.S. §§ 38-22-109, 38-22-110
IllinoisSubs: notice to owner within 90 days after completing work (60 days for owner-occupied homes)4 months after completion to bind buyers and lenders2 years after completion770 ILCS 60/7, 60/9, 60/21, 60/24

How long each state gives you

The same job in each state: a contractor hired by the owner on a commercial project whose last day of work was March 2, 2026.

Days from last work to the lien deadline, by stateCalifornia: 90 days; Florida: 90 days; Georgia: 90 days; Washington: 90 days; Arizona: 120 days; North Carolina: 120 days; Colorado: 122 days; Illinois: 122 days; Texas: 135 days; New York: 245 days0 days90 days180 daysCaliforniaCalifornia: lien due 90 days after the last day of work90FloridaFlorida: lien due 90 days after the last day of work90GeorgiaGeorgia: lien due 90 days after the last day of work90WashingtonWashington: lien due 90 days after the last day of work90ArizonaArizona: lien due 120 days after the last day of work120North CarolinaNorth Carolina: lien due 120 days after the last day of work120ColoradoColorado: lien due 122 days after the last day of work122IllinoisIllinois: lien due 122 days after the last day of work122TexasTexas: lien due 135 days after the last day of work135New YorkNew York: lien due 245 days after the last day of work245
Example: a contractor hired by the owner on a commercial project whose last day of work was March 2, 2026, with no notice of completion recorded. California and Arizona count from completion of the whole project, so their real deadline can be later. Calculated with our lien deadline calculator from each state’s statute.

Worked example: Texas

Texas counts to the 15th day of a later month, so the month you worked matters more than the day. Take a subcontractor on a commercial project who worked from January 20 to March 2, 2026, and hasn’t been paid for any of it.

StepRuleDeadline
Notice for January work15th day of the 3rd month after JanuaryApril 15, 2026
Notice for February work15th day of the 3rd month after FebruaryMay 15, 2026
Notice for March work15th day of the 3rd month after MarchJune 15, 2026
Lien affidavit15th day of the 4th month after MarchJuly 15, 2026
Lawsuit1 year after the last day to fileJuly 15, 2027

On a residential project, each step moves one month earlier. Source: Tex. Prop. Code § 53.052, for contracts entered on or after January 1, 2022.

Free tool
Get these dates for your own job, in any of the 10 states.
Open the calculator

Notices before the lien

Many states won’t let you file a lien unless you sent a notice early in the job, often before anyone knows there will be a payment problem.

  • California and Arizona: a 20-day preliminary notice. Sent late, it only covers work from the 20 days before it was served.
  • Florida: a Notice to Owner within 45 days of starting. Missing it is a complete defense to the lien.
  • Texas: a notice for each month of unpaid work, by the 15th day of the third month after that month (second month on residential jobs).
  • Washington: a notice to owner that only covers the 60 days before it is sent.
  • Colorado: a notice of intent at least 10 days before recording the lien.

After you file

Filing the lien is not the last step. Most states require you to send the owner a copy within a short window, and every state sets a deadline to file a lawsuit to enforce the lien. Miss that and the lien expires. In California that is 90 days after recording; in Washington, 8 months; in Florida, 1 year.

What the research shows

Industry survey · 202656%

of subcontractors say they missed a critical lien deadline in the past two years.

Source: Siteline, 2026 State of Subcontractor Billing Report
Industry report · 2024$280 billion

is the estimated cost of slow payments to the US construction industry in 2024.

Source: Rabbet, 2024 Construction Payments Report
Florida statute45 days

to serve a Notice to Owner in Florida. Missing it is a complete defense to the lien.

Source: Fla. Stat. § 713.06

Questions

What is a mechanics lien?

A legal claim against the property you improved, available to contractors, subcontractors and suppliers who aren’t paid. It can force payment from the property owner, but only if every notice and filing deadline is met.

Does the deadline start from my invoice date?

No. Deadlines run from when work was performed or materials were delivered, or from completion of the project, depending on the state. Invoice dates don’t count.

Can warranty work extend the deadline?

Generally no. Corrective or warranty work does not restart the clock in most states.

What happens if I miss a deadline?

In most states the lien right is lost for that work. You may still sue the party you contracted with, but you lose the security of a claim against the property.

Are public projects different?

Yes. Public property usually can’t be liened; claimants use payment bond claims, which have their own notice deadlines.

Sources

This guide gives general information, not legal advice. Lien laws change and depend on your contract and project type. Confirm with the current statute or a construction attorney in your state. Last checked October 21, 2026.